Hurlingham Academy


Replacement of Boiler Plant and BMS Control system

Project site:

Hurlingham Academy, London, SW6 3ED

Client:

United Learning Trust, London Region 1

Contract Value:

£416,834.00

Contract Type:

JCT Minor Works Building Contract with Contractor's Design MW2016

 Strip out works

  • Oil boilers, Flues, pump sets, Controls, wiring and pipework.
  • Existing Calorifiers and 20,000 Lts Oil Tanks.

Supply and Install

  • 2 No Remeha Gas Ace 500 KW gas fired condensing boilers and shunt pumps.
  • New flue liners within existing 40m chimney
  • 1050 KW Plate Heat Exchanger
  • Lochinvar 400Lt Gas fired Condensing Water Heater
  • 4 No. Twin Invertor Secondary pump sets
  • Copper Pipework, Fittings, Valves, and Insulation
  • New 100m Gas supply from meter for new boilers
  • Flamco twin system pressurisation unit
  • 2 No. 450Lt Expansion Vessels
  • Magnetic filtration and dosing pots.
  • Expansion vessels, pipework, and Insulation.
  • Electrical Trunking, wiring, Switchgear and earth bonding.
  • New lighting with Emergency Luminaires
  • Gas Solenoid valve and Gas Detection Alarm PanelReplacement of corridor cast iron radiators with LST steel panel radiators
  • Complete New Control panel, Trend BMS controls system, c/w 4 No Space Zone Sensors, remote monitoring, and associated equipment
    • Builders work in connection with the new installation.
    • Hire of Temporary Oil Boiler for duration of the contract works.